DTE Gas Main Relocation: Hydro Station/North & South Hydro Parks
On Monday, October 19th, DTE Gas will close Bridge Rd between Grove Rd and Textile Rd in Ypsilanti Township in connection with the Ford Lake Dam Project. Access to North Hydro Park will be maintained from the north. The work is expected to be complete in approximately 4 weeks.
Note: Bridge Rd will reopen Election Day, Tuesday, November 3rd. DTE will resume construction work and close Bridge Rd on Wednesday, November 4th - Wednesday, November 11th.
If you have any questions concerning this work, please contact Kyce Soerries, Corby Energy Project Manager, at (734) 547-9237 or ksoerries@corbyenergy.com.
DTE Gas is relocating the existing gas line on the bridge and dam (originally runs down Bridge Rd to Textile Rd) that spans the Huron River at the east end of Ford Lake. The gas line relocation is being done to improve safety and reliability to the gas line network and will be safer to do future maintenance and concrete work on the dam. This work has started and is planned to take 7 months to complete. Anticipated finish date is November 2026.
Note: Bridge Rd will reopen Election Day, Tuesday, November 3rd. DTE will resume construction work and close Bridge Rd on Wednesday, November 4th - Wednesday, November 11th.
If you have any questions concerning this work, please contact Kyce Soerries, Corby Energy Project Manager, at (734) 547-9237 or ksoerries@corbyenergy.com.
DTE Gas is relocating the existing gas line on the bridge and dam (originally runs down Bridge Rd to Textile Rd) that spans the Huron River at the east end of Ford Lake. The gas line relocation is being done to improve safety and reliability to the gas line network and will be safer to do future maintenance and concrete work on the dam. This work has started and is planned to take 7 months to complete. Anticipated finish date is November 2026.
-
Improves gas line safety and service reliability to DTE customers
-
Improves safety for dam operations and compliance
- Safer for maintenance work around the dam
DTE Update Letter: July 15, 2026


Project Description:- Install main from north of Ford Lake Hydro Dam to south of Ford Lake Hydro Dam through the North and South Hydro Parks.
- Cut, cap, and abandon gas main from Textile Rd to the south end of Ford Lake Hydro Dam bridge
- Cut, cap, and remove gas main from the west side of Ford Lake Hydro Dam bridge
- Cut, cap, and abandon gas main from near the North Hydro Park Driveway to the north end of Ford Lake Hydro Dam bridge
Park shelter rentals will not be available for the Summer of 2026.
While South Hydro Park remains open for public use, a temporary “No Parking” sign, has been put up to prevent potential public vehicles from blocking access to the gas pipe and equipment currently staged in South Hydro Park.